Eastern and Western Peripheral Expressways: 11 years after launch, ‘Diwali gift’ for 4 states to take off

m

A few kilometers away from Rajiv Gandhi Education City, Kundli in Sonipat — where Prime Minister Narendra Modi Thursday lay the foundation for three mega highway projects — remnants of an unfinished road project and resultant diversions create a traffic snarl. It was designed to be the Western Peripheral Expressway, initiated almost 11 years ago to ease congestion as well as air pollution levels in the national capital.

It has stood lifeless for years and is finally set to see hectic activity in the coming months.

 The Eastern and Western Peripheral Expressways — each about 135 km long — were planned in 2006 following a Supreme Court order to form a ring road outside Delhi for channelling non-Delhi bound traffic, bypassing the national capital. With rising air pollution levels and road accidents in Delhi, the need for the two expressways was highlighted even more.

The project is set to primarily benefit Haryana and Uttar Pradesh, as it will open up hinterlands for developing commercial areas and townships along the expressways, apart from generating revenue. It is also expected to improve air pollution levels in Delhi and decongest the national capital. While the Eastern Peripheral Expressway envisages to provide signal-free connectivity between Ghaziabad, Faridabad, Gautam Budh Nagar (Greater Noida) and Palwal, the Western Expressway connects Kundli to Palwal via Manesar in Haryana. Last year, the Delhi government had moved a plea in the Supreme Court to issue a directive for completion of the two expressways in a time-bound manner. The Delhi government had complained that it was asked to bear 50 per cent cost of the Rs 844-crore project but the total project cost had been revised to Rs 3,589.56 crore. It had requested the court to fix a cut-off date, up to which it had to bear the land acquisition price. The Delhi government had said that 10 years after committing to the project, Delhi was bearing the brunt of the continued movement of transit traffic, its hazards and resultant pollution, as well as the repeated demands for release of additional funds for the expressways. “The Western Peripheral Expressway is about 68 per cent complete and the Eastern Peripheral Expressway is yet to take off,” it had then told the court. Union Minister for Road Transport and Shipping Nitin Gadkari Thursday said that the Eastern and Western Peripheral Expressways will help decongest the national capital by 50 per cent and reduce air pollution level drastically. “Stalled for several years, the Western Peripheral Expressway on completion will provide high-speed link of northern Haryana with its southern districts like Gurgaon, Faridabad and Palwal. I can assure the Prime Minister that in the next five years my ministry will provide direct and indirect employment to 50 lakh youths,” he said, adding “The Eastern Peripheral Expressway will be the first access-controlled highway in the country.” Gadkari also referred to the earlier UPA government, saying, “So far, only 2 kms of roads were being built per day, whereas ever since our government took over, we have been building 18 kms per day. From 96,000 kms of national highways network, we will take it up to 1.5 lakh kms by December this year. Single roads will be made double-lane; two-lanes will be converted into four and four-lanes into six or eight.” The three highway projects were a ‘Diwali gift’, said Haryana Chief Minister Manohar Lal Khattar. The gifts would benefit not only Haryana but also Delhi, Rajasthan and Uttar Pradesh as it would connect all four states, he said. These projects include the Western Peripheral Expressway, Eastern Peripheral Expressway and the eight-laning of the Highway Section from Mukarba Chowk in Delhi to Panipat. – See more at: http://indianexpress.com/article/cities/delhi/eastern-and-western-peripheral-expressways-11-years-after-launch-diwali-gift-for-4-states-to-take-off/#sthash.VG8sFMcT.dpuf

Comments are closed.