PM’s package for Bihar– 2015 (August 18, 2015)

s2015081868651

s2015081868647

I. National Highways.

A. Projects under process for award/bidding stage.

Sl. No. NH No. Project Name Length (km) TPC (in Rs. Cr.)
1 82 Biharsharif – Barbigha – Mokama section of NH-82,NHDP Phase-IV 55 399.54
2 30 4- laning of Patna-Koilawar section of NH 30 33 492
2 30 4- laning of Patna-Koilawar section of NH 30 33 492
3 30&84 4- laning of Koilawar- Bhojpur section of NH-30 and NH-84 44 750
4 84 4 laning of Bhojpur-Baxar section of NH-84 48 595
5 31 4 laning of Bakhtiyarpur-Mokama section of NH-31 45 970
6 31 New 4-laned bridge across river Ganga at Mokama on NH-31 09 520
7 31 4lane of Simaria – Khagaria on NH-31,NHDP Phase-III 60 1062.58
8 30A km 0.0-km 69.6 of Fatua-Harnaut-Barh section of NH-30A 71.8 591.2
9 104 Upgradation of Sheohar-Sitamarhi-Jaynagar-Narahiya (km 40-217) of NH 104 in three packages 179.95 701.44
10 106 Upgradation of Birpur-Bihpur (km 0-106) section of NH-106 105.2 575.34
85 30 2-laning with paved shoulder of Gopalganj – Chhapra section 94 748.06
12 28B Widening and strengthening to 2-lane with paved shoulder & geometric improvement Betiah -Khushinagar Section from km 25.00 to km 40.00 on EPC mode 15.00 88.61
13 28B Strengthening and Widening to 2 Lane with Paved Shoulder from km 65 to 97 on EPC mode 33.00 206.80
14 102 2-laning with paved shoulder of Chhapra – Rewaghat – Muzaffarpur 73 420.58
15 133 Strengthening and Widening to 2 Lane with Paved Shoulder from km. 0.00 to 10.903 10.90 28.04
16 327A Strengthening & Widening to 2 Lane with Paved Shoulder from km. 0.00 to 25.010 on EPC mode 25.01 77.55
17 327E Strengthening & widening work of existing 2-Lane to two lane with paved shoulder from Km. 93.612 to Km. 98.000 4.39 64.52
18 57A 4 laning of Forbesganj-Jogbani section of NH-57A 9 200
19 83 4 laning of Patna – Gaya – Dobi section of NH 83 with JICA ODA loan assistance 127 1231.98
20 80 Construction of Bhagalpur Bypass 13 268
Total 1055.25 9991.24

B. Projects in the Pipeline.

Sl. No. Project Length (Km) Cost (Rs. Crore)
1 4 laning of Mokama-Khagariya section of NH-31 60 810
2 Bridge at Munger 18.69 2361.87
3 Development to 2-laned with paved shoulder of Maheshughat-Saharsa-Purnia section of NH-107 171 1000
4 Development of Manjholi-Chirkot section 65 700
5 4/6 laning of Patna Ring Road 65 1500
6 4 laning of Kishanganj Bypass at NH-31 20 250
7 4-laning of Munger-Mirzachowki section of Nh-80 120 1200
8 Development to 2-lane with paved shoulder of sections on NH-2C, NH80, NH81, NH99 and NH527 A. 116 680
9 Construction of MG Setu with JICA assistance 5.6 2800
10 Construction of bridge across Kosi river an Km 136 of NH-106 20 3000
Ensuring Connectivity Across Major Rivers
11 Bridge on river Ganga connecting Manihari in Bihar to Sahibganj in Jharkhand 2000
12 Bridge over river Sone connecting Panduka(Nauhata) on NH-2C in Bihar and Shrinagar(Garhwa District) in Jharkhand 2000
13 A new 4-laned bridge on river Ganga parallel to existing MG Setu 5000
14 Improving Connectivity- Declaration of New National Highway and its development 436.58 6600
15 New National Highway connecting Buxar on NH-84-Chausa-Ramgarh-Mohania on NH-2 64 960
Sl. No. Project Length (Km) Cost (Rs. Crore)
Projects under “Bharatmala Programme”
16 Roads connecting Raxaul and Sonbarsa (Parallel to Indo-Nepal Border) 90 1800
17 Chakia- Bargainia connectivity 50 1000
Projects For Improving Connectivity Of Places Of Religious Interest
18 Development of Rampur -Khajuriya -Kesariya end of NH-722 to 4 lane standard 58 1160
19 Development of Umgaon-Basopatti-Benipatti-Rahua-Madhubani-Rampatti-Awam-Laufa-Bheja-Supaul-Mehsi-Saharsa which connects Uchchait Bhagwati Sthan to Mehsi Taraesthan to 2 lane with paved shoulder or 4-lane standard with a bridge over river Kosi 160 5000
20 Development of Ram-Janki Marg as already declared recently part of which falls in Bihar from UP Bihar Border to Siwan-Madhubani-Sitamarhi-Indo-Nepal Border to 4 lane standard 200 4000
Rail Over Bridge (ROB)
21 12 ROBs 900
Total 1719.87 44721.87
Grand Total for NH 2775.12 54713.11

II. RURAL DEVELOPMENT

To complete about 22,500 km of PMGSY roads in Bihar 13820

III. Petroleum and Natural Gas

1 The Barauni Refinery would be expanded from 6 million tons to 9 million tons 12000
2 A Polyproplene Recovery Plant for petro-chemical products would also be set up. 3500
3 The implementation of the 617 Kms pipeline relating to Bihar in Jagdishpur-Haldia pipeline 2300
4 Raxaul Amlekhganj pipeline 200
5 Extension of Paradip-Haldia- Durgapur LPG pipeline 1800
6 New LPG Plant at Muzaffarpur 110
7 Creation of additional capacity for LPG plant at Patna 15
8 Implementation of BS IV fuel at Barauni Refinery 1500
9 Augumentation of Patna LPG Plant from 60 to 120 TMTPA 45
10 Upgradation of Purnea LPG Plant 6
Total   21476

IV. CIVIL AVIATION

1 Construction of a Greenfield Airport at Patna 2000
2 Development of Gaya Airport for Airbus 321-200 type of aircraft operations with new terminal building and apron, runway extension, CAT-I approach lighting 300
3 Development of Raxual Airport for ATR-72 / Q-400 type of aircrafts for VFR operations 250
4 Development of Civil Enclave at Purnea Airport for Airbus 321-200 type of aircraft 150
Total   2700

V. HIGHER EDUCATION

1 Establishment of a Central University near Bhagalpur at the historic site of Vikramshila University 500
2 Establishment of IIM, Bodh Gaya 500
Total   1000

VI. SKILL DEVELOPMENT

1 To train one lakh youth under Pradhan Mantri Kaushal Vikas Yojana 300
2 25,000 youth to be trained in Power sector
3 Mega Skill University in Bihar 1250
Total   1550

VII. AGRICULTURE

1 Upgradation of PUSA (Bihar) to the level of a Central Agricultural University 400
2 Development of fisheries 200
3 Farm Water Management (Micro irrigation, creation of water resources) 750
4 Development of Storage Capacity 600
5 Farm Mechanization 600
6 Seed production systems 300
7 National Research Centre on Integrated Farming System, Motihari, Bihar 30
8 Construction of new godowns at Supaul, Madhepura, Hazipur and Chakia Bazar 214
Total   3094

VIII. RAILWAYS

A. Doubling/Tripling of Railway Line.

1 Rampur Dumra – Tal – Rajendrapul Addl Bridge and doubling – 14 Km length 938
2 Hajipur – Bachwara – 72 kms 756
3 Samastipur – Darbhanga 38 kms 399
4 Kiul – Gaya 123 kms 1292
5 3rd line between Dhanbad – Sonnagar (partly in Bihar ) – 429 kms 4725

B. Railway Electrification.

1 Kiul – Tilaiya 87 kms 85
2 Valmikinagar – Narkatiaganj-Sugauli-Muzaffarpur including Sugauli-Raxaul 240 kms 397
3 Ammapali Halt – Kiul including Tinpahar-Rajmahal (Part of Bonidanga link cabin/Bonidanga-Barharwa- Sahibgang-Kiul section incl Tinpahar-Rajmahal) Length 247 kms 279
Total   8870

IX. POWER

1 Construction of 1300 MW Power plant at Buxar {PIB has recently appraised the project and recommended Rs. 437 cr as pre-investment activity to kick start the project.} 10000
2 Deen Dayal Upadhyay Gram Vidyut Yojana 5880
3 Under Integrated Power Development Scheme (IPDS). 250
Total   16130

X. TELECOMMUNICATION – DIGITAL BIHAR

1 1000 new BTS (towers) to be installed in Bihar 250
2 Setting up of 2 new STPI centres (Software Technology Park of India) in Darbhanga and Bhagalpur and Rural BPO scheme for small towns and rural areas. This will help in promoting the IT entrepreneurs and start ups in Bihar. 20
3 Setting up 2 new NIELIT Centres in Muzaffarpur and Buxar apart from upgrading the existing centre in Patna, Medical Incubator at IIT Patna, Electronics and ICT Academy at NIT Patna. 14
4 Electronic Manufacturing clusters in Bihar for which 50% subsidy for greenfield and 75 % subsidy for Brownfield EMCs are available. 150
5 30 WiFi hotspots will be rolled out in Bihar, by BSNL at prominent tourist places such as Rajgir, Vaishali, Gaya, Nalanda and Patna 15
Total   449

XI. TOURISM

1 Vaishali and Bodhgaya development alongwith other places in buddhist circuit including Vikramshla 200
2 Sultanganj to Deoghar project 50
3 Patna Sahib under Prasad 50
4 Mahatma Gandhi Circuit 50
5 Ramayan Circuit 100
6 Jain Circuit including Champa puri 50
7 circuit for Mandar Hills and Ang Pradesh 50
8 IITTM chapter in Bihar 50
Total   600

XII. HEALTH

1 Upgradation of 3 Medical colleges at Patna, Bhagalpur & Gaya under PMMSY in Bihar 600
Grand Total of the Package   1,25,003

-Income Tax Relief on new capital investment in the form of Additional Investment Allowance and Higher Additional Depreciation for investment in backward areas of Bihar.

Other Investments: Rs. 40,657 crore

1. Unspent amount of 2013 Special Plan (of Rs. 12,000 crore): Rs. 8,282 crore

2. Ongoing works of National Highways: Rs. 12,375 crore

3. Ultra Mega Power Project (UMPP) in Banka under PPP: Rs. 20,000 crore

Comments are closed.